North Park Central and the North-South Corridor: What LTA's Revised 2029 and 2031 Opening Means for Yishun Drivers
Frasers Property's 2 September 2026 release for North Park Central, its redevelopment of Yishun 10 at 51 Yishun Central 1, names "convenient access to the upcoming North-South Corridor" as one of the site's selling points. Two weeks later, on 17 September 2026, the Land Transport Authority pushed back the corridor's opening by about two years. If driving into the city is part of why you are looking at Yishun, here is what the new schedule says and how it lines up with this project's own dates.
What LTA changed on 17 September 2026
| Section | Previous target | Revised target |
|---|---|---|
| Viaduct, Admiralty Road West to Lentor Avenue | 2027 | Opens in phases from 2029 |
| Tunnel, Lentor Avenue to East Coast Parkway | 2029 | Opens in phases from 2031 |
LTA put the slip down to harder rock and difficult ground at Gambas Avenue and Woodlands Avenue 8, fractured rock under the live North-South Line tunnel at Novena, and harder-than-expected rock at Thomson. As of August 2026, LTA says more than 90% of the foundation works on both the viaduct and the tunnel were complete. On 6 October 2026, Transport Minister Jeffrey Siow told Parliament the revised plan is phased openings from 2029 for the viaduct and from 2031 for the tunnel.
What the corridor is
LTA describes the North-South Corridor as a 21.5km route, an 8.8km viaduct and a 12.3km tunnel, linking the northern region to the city and serving towns including Sembawang, Yishun, Ang Mo Kio, Toa Payoh, Novena and Rochor. It will connect to the Seletar Expressway, Pan-Island Expressway and East Coast Parkway, and is meant to ease traffic on the Central Expressway and on Thomson and Marymount Roads. Once traffic moves onto it, the roads at ground level along the route are to be given over progressively to walking, cycling, buses and community space. LTA's ramp locations are still subject to detailed design; contact Davis Ng for the nearest ramp once they are final.
Lining the two timelines up
- Mid-2027: Frasers' targeted launch for North Park Central. The minister expects the noisiest, dustiest structural works on the corridor to be largely done by the end of 2027, and LTA says more of the work moves underground from 2027.
- 2028: LTA starts handing back roads, footpaths and other spaces taken up by construction. The minister gave Lentor Avenue and Sembawang Road as examples of roads whose surfaces should be fully reinstated by mid-2028.
- From 2029: the viaduct section, the northern part of the corridor, opens in phases.
- 2031: Frasers' targeted completion for North Park Central, and the year the tunnel to the East Coast Parkway starts opening in phases.
On these targets, the full route into the city would only be starting to open around the time the homes are completed. Both are targets, and LTA has revised the corridor's timeline before, so do not count on it being fully open when you collect your keys.
How to weigh it
- If you drive to the city: treat the corridor as a benefit that arrives after you move in, not on day one. Plan your daily drive around the roads that exist today.
- If you mainly take the train: the corridor matters less. Frasers places the site next to Yishun MRT Station (North-South Line) and the Yishun Integrated Transport Hub, with underground access to Northpoint City; the location page covers the surroundings.
- If you are buying to rent out: the corridor's phased opening around 2031 is one more reason to ask how the area will look in the years after completion, not only at completion.
Prices have not been released. Watch the North Park Central price page for Frasers' price list, and register on the showflat page to hear when previews are announced. The floor plans page will carry layouts once Frasers publishes them.
Get North Park Central Updates First
Get the latest price list, available units and floor plans for North Park Central — no obligation.